GENERAL
SPECIFICATION OF QUALITY
CONTROL FOR INSTALLATION OF PIPE BY HIDROMECHANIC
SUNK FOR THE COLLECTOR INDECO II |
EXCAVATION AND SUNK PIPE
A.- EXCAVATION DIMENSION
The excavation will have enough dimension that allows the efficient displacement
of the operations of having sunk so that it allows to give the enough
space to place the pipe in all its external perimeter as here it indicates.
The appropriate determination of the excavation diameter will be under
the contractor's responsibility.
B.-
SUNK PIPE.
The hydraulic jacks that are used will have enough capacity for push the
pipe and shield through the floor. The operation of this pistons will
have the appropriate place so that each one of them receives an uniform
pressure.
The pipe to sink will be supported in a structure-guide, in order to be
able to support and to guide the pipe according to the vertical and horizontal
alignment of the project.
-The pipe during the execution of the work will sink of the end and dilute
below preferably.
-The space understood between the external wall of the pipe and the floor,
he/she will stay busy of bentonita Iodo or another type of lubricant during
the operations of the excavation and sunk of the pipe, in order to reduce
the friction and the possibility of the stagnation of the one sunk; as
well as to avoid that the pipe undergoes an excessive load of push and
it can be damaged.
-In case during the operations of having sunk, a tube section is damaged,
the contractor will proceed to repair this damage like is indicated next:
(a) The smallest damages will repair in place.
(b) The pipe that is damaged severely, will
be demolished in sections ring of 50 cm of longitude, subsequently of
the one sunk corresponding; having the necessary care in order to not
to alter the floor, pavements in the surface or adjacent structures..
-The displacement of the excavation by means of the shield being in a
simultaneous way will should to the push of the pipe in all moment, for
any reason you will dig previously to the application of the force of
having sunk.
-The meetings of union of the pipe will be sealed tightly, by means of
the use of rubber packing.
-The meetings of union of the pipe, they will quilt by means of a wooden
ring that has the capacity to transmit the load of having sunk in an uniform
way, in order to avoid that it is damaged the pipe or the meetings of
union of the same one.
-In order to assure the termination of the sunk of the pipe between light-shaft
and light-shaft, it will settle the number intermediate of stations having
sunk necessary under the contractor's determination and under the strict
responsibility of the same one.
CONTROL OF THE VERTICAL AND HORIZONTAL
ALIGNMENT
A.-EXECUTION CONTROL
-The dependence will indicate the location of the references of the line
physically and of the level banks. The contractor will verify these references
and level banks previously to the beginning of the work, and in the event
of finding some error or discrepancy, this you/he/she will report it to
the dependence, in order to clarify it.
-The contractor will execute the work according to the references and
established level banks for the dependence
-The contractor will be completely responsible for the precision of the
execution of the work, including the location of the structures, excavations,
vertical and horizontal alignment of the pipe.
-The contractor will locate the control apparatuses for the guide of the
tunnel in such a way that these they are not affected by some movement
of the floor or for the vibrations that generates the team.
B.-ESTABLISHMENT
OF THE FLOOR
-The contractor will foresee according to the project the vicinity of
the location of structures, pavements and existent services. It will have
the necessary cautions in order to avoid they are damaged or happen an
establishment in them.
-In the event in that some sinking, the dependence is detected it will
be able to order the temporary suspención of the work. Before proceeding
to continue the work the contractor it will correct the causes in the
method or in the team that caused this stablishment.
C.-LINE
AND SLOPE
-The excavation and sunk has a permissible tolerance of 10 mm. in the
slope and of 30 mm for each 30 mts.
-When the excavation is exceeded of these tolerances, the contractor will
carry out the necessary corrections to be relocated inside the project.
|